• Each change request form (CRF) will be numbered uniquely to facilitate tracking. The CRF will be handed to the Transaction Junction project manager who will conduct an impact |
• Each change request form (CRF) will be numbered uniquely to facilitate tracking. The CRF will be handed to the Transaction Junction project manager who will conduct an impact |
Line 14: | Line 13: |
• The CRF will contain the following: • The reason for the change • Consequences and impact of the change • The available options • The effect of each option on the business case, risks, resources, delivery dates and budget • The recommendation }}} |
• The CRF will contain the following: • The reason for the change • Consequences and impact of the change • The available options • The effect of each option on the business case, risks, resources, delivery dates and budget • The recommendation |
Change Control Process
- Standard items
Any identified changes that may affect the approved project plan will be documented on formal change request forms and reported to the respective Project Managers for approval. The process will comprise:
- • Each change request form (CRF) will be numbered uniquely to facilitate tracking. The CRF will be handed to the Transaction Junction project manager who will conduct an impact
assessment
- • The CRF will contain the following:
- • The reason for the change • Consequences and impact of the change • The available options • The effect of each option on the business case, risks, resources, delivery dates and budget • The recommendation
...